Core ConceptsGlossary & Abbreviations

Platform Glossary & Abbreviations

Alphabetical Watchmen definitions and exact English/German screen labels, including OEE, AVL, PRO, PDA/BDE, MA/AA, OP/AG, and KB/WDB.

Find the Label You See on Screen

Each entry keeps English and German interface labels together. Search for the exact caption, such as PRO, AA, AG, WDB, or Vorber. PRO means Performance; AA is Work Scrap; AG is the operation-priority chip; WDB is the Knowledge Base. Definitions link to the page where you can use the concept.

Related references: calculations and roles and access.

0–9 / +

+1day / +1week / +1month / +1Tag

Quick date-shift controls on order and access-key forms; the German forms use Tag, Woche, and Monat.

Learn more.

1v1 / 1 V 1 / Versus

Older names for Versus, the side-by-side machine comparison page.

Learn more.

2FA / OTP

Two-factor authentication and a one-time password: the second sign-in step uses a six-digit email or authenticator code.

Learn more.

A

AA / Work / Arbeits-Ausschuss

Work Scrap: rejected parts caused by processing rather than the material. Kept separate from MA material scrap.

Learn more.

Accessibility patterns

Optional dots for Idle and diagonal lines for Off, making states distinguishable without color alone.

Learn more.

Active Sessions

Devices signed in to your account. Individual sessions can be signed out remotely.

Learn more.

Active shift

An Active shift starts at idle, production, or preparation and ends according to the machine’s duration settings. The assigned shift group is not used. Switching on removes scheduled shifts from today onward but keeps shifts already recorded today. Switching off ends the running active shift immediately and creates scheduled shifts from the group from today.

Waiting for the next active shift and waiting for machine start mean no new active shift has started yet. Planned shifts from the assigned group appear until the machine begins idle, production, or preparation. The machine still uses active shifts.

Learn more.

AG / OP / Arbeitsgang / Operation

An operation is one production activity in a work order. English labels now use “operation” where they previously said “step”, such as Operations of this order. The dashed OP chip (AG in German) shows operation priority; P shows order priority.

Learn more.

AI / KI / Artificial intelligence

Artificial intelligence (Künstliche Intelligenz), used by the Beta Watchmen AI Assistant.

Learn more.

AI Assistant / Watchmen AI / AI Chats

Beta chat assistant. Documentation only uses platform docs; Context-aware may query data areas enabled by an admin.

Learn more.

Alert Rules

Classic machine alerts using conditions, recipients, and email, SMS, or webhook channels; operators cannot access the page.

Learn more.

All Day / Planned

Analytics scope: a full 24-hour day versus scheduled shift time. Compare the same mode.

Learn more.

API-Access Keys

Keys used by other systems to access the platform; a newly created key is shown only once.

Learn more.

Assignment / Zuweisung

One operation placed on a machine or in a hall pool; intervals record the actual work on it.

Learn more.

Assignment view modes

All Open has no date filter; Time Window + Open selects open work within ±1/3/5/7 days; Time Window + All Statuses includes completed and cancelled work.

Learn more.

Auto-Arrange

Automatically rearranges overlapping future assignments while leaving in-progress work unchanged.

Learn more.

Auto. / Automatically detected

Sensor-detected values, as in Cycles (Auto. / Planned). It does not mean operator-entered quantity.

Learn more.

Automator

Admin-only rule engine with scope, conditions, timing, response, and an event inbox.

Learn more.

AVA

The sensor device attached to a machine. Its full name is not expanded in the interface. A machine without an assigned AVA has no live sensor state or KPIs.

Learn more.

AVA assignment

Connection of an AVA device to a machine. Several devices can be assigned; dragging changes their priority.

Learn more.

Avg. / Ø / Average

Average value. Distinguish the three cycle-time averages and their different denominators.

Learn more.

Avg. Cycle Duration

Total interval duration divided by detected cycles, including pauses and loading.

Learn more.

Avg. Cycle Time (Operator Input)

Production time divided by the quantity entered by the operator.

Learn more.

Avg. Production Cycle Time

Active production time divided by detected cycles.

Learn more.

AVL / Availability / Verfügbarkeit

Share of total recorded machine time in Production. AVL remains AVL in German and appears on gauges, Hall Plan figures, and kiosk bars.

Learn more.

B

Best operation sequence

Best operation sequence in Improve plan searches for fewer late orders, then less total delay, then earlier expected ends. If these tie, order priority favours more urgent orders finishing first without changing their priority; fewer changes decide last. Keep priorities changes no priority. Least delay seeks the best result. Fewest changes limits the searched sequence to at most 3 moves. Recommended marks the suggested option. With Delivery date first, this option is greyed out in Gantt and no search starts. You can still compare the fixed rules.

Learn more.

Back to pool

Back to pool returns unfinished work to the machine’s own hall pool from Data Acquisition V3. It is also the confirmation button in Assignment Planner after you drop a started, stopped card onto a hall pool. Administrators and users with access to the Orders page can choose any hall pool there. Other users can only return work to the pool of its current machine’s hall. Everyone needs access to the step’s current machine. If work has started, its times and good parts stay on the original machine and only the remainder is passed on. Reason (optional) gives the next operator a note.

Learn more.

BDE access templates

BDE access templates are shared settings for selected machines’ Data Acquisition V3 pages. Administrators manage them in the Admin Panel. Each machine uses at most one template. The rules apply to everyone on that BDE page, including administrators, without changing other pages.

  • Always shown keeps selected fields visible.
  • Always highlighted keeps selected fields highlighted when they are visible.
  • Use a fixed sorting and Use a fixed auto-refresh replace personal choices on those machines while keeping them saved.
  • Allowed on the BDE page controls which actions you can use. On means allowed. Blocked action buttons and edit icons stay visible but disabled. Locked for this machine (BDE template). explains the restriction on hover or tap. A blocked status stays visible but opens no menu.
  • Set by the template marks a locked choice. Sorting is set by the template marks sorting you can review but cannot change on the BDE page.

Learn more.

BDE / PDA / Betriebsdatenerfassung / Production Data Acquisition

English PDA and German BDE refer to the same operator screen for starting work and booking quantities. PDA Entry is BDE-Eintrag; PDA Assist is BDE Assist.

Learn more.

Booked time

Booked time splits a step’s recorded work into Preparation and Production. Compare it with Machine states to see what the machine did during that work.

Learn more.

C

Can move / Place

Clear Can move to keep an existing operation at its exact queue place in a proposal. Pool operations use Place instead: clearing it leaves the operation in the pool. Fixed-rule choices in Improve plan do not offer Can move.

Learn more.

Card Display Settings / Columns / Highlight

Per-user choices of card fields and highlights. They change the display, not the underlying work. On Data Acquisition V3, a machine template can require extra fields and highlights.

Learn more.

CHG / GEÄ / Changed

ERP check badge: an existing record would be updated by the import.

Learn more.

Clear duration

How long an Automator condition must stay normal before an event can clear.

Learn more.

Company Sorting Default

The sorting chosen by an administrator through Save as company default in Assignment Planner. It includes the mode, shared rules, and the Moves choice for where moved orders land. People without their own sorting start with it. Data Acquisition uses the mode and shared rules only. A reset copies the current company choices into your own settings; later company changes do not replace them.

Learn more.

Concurrent order prompt

Confirmation shown when starting an assignment while another is already running.

Learn more.

Condition group

Automator conditions combined with AND or OR; groups may be nested.

Learn more.

Cooldown

Waiting time after an Automator alert before alerting again. Without a cooldown, it can alert again as soon as the condition returns.

Learn more.

CO₂ / Carbon dioxide

Carbon dioxide estimate in Organization Statistics, based on optional Sustainability Check inputs.

Learn more.

CSV / XLS / XLSX

Spreadsheet formats accepted by ERP Uploads. CSV and XLSX are also offered for downloads.

Learn more.

Cumulative

Quantity-entry mode using the machine's entire counter reading, not this interval's increment.

Learn more.

Customer / Kunde

The recipient of the order, identified by a name or customer code.

Learn more.

Cycle

One sensor-detected machine cycle, such as a stroke, part, or batch. Cycles Per Product defines how many make a finished part.

Learn more.

Cycles found outside the intervals

Detected cycles belonging to no recorded work interval; useful for explaining count differences.

Learn more.

Cycles Per Product / Press per Product / Zyklen / Presshübe pro Produkt

Number of machine cycles needed for one finished part.

Learn more.

D

Distribute to machines

Distribute to machines proposes machines and places for selected hall-pool operations. Existing machine work keeps its relative sequence. The summary compares late orders with leaving the work in the pool. Nothing changes until you apply.

Learn more.

d / ±1d / T / Days

Days in time windows and Due in labels. ±1d means a one-day window in each direction.

Learn more.

Dev. / Deviation / Abweichung

Actual time minus planned time. A negative time deviation means faster than planned.

Learn more.

Dictate

Voice input for AI chats and Knowledge Base notes.

Learn more.

Displays

Registered hall monitors with last-seen time and network information.

Learn more.

doc / Dok. / Document count

Document count in the Knowledge Base, such as 1 doc or 1 Dok.

Learn more.

Downtime / Stillstand

Time in Idle or Off. Label it with a reason to explain the interruption.

Learn more.

Downtime Analysis (labeled)

Downtime grouped by its assigned reasons, not just by state.

Learn more.

Downtime Reduced

Reduced idle time above a machine-specific best-days baseline; it is not all idle time.

Learn more.

Dur / Duration / Dauer

The duration of a planned or recorded period; check whether the field is planned or actual.

Learn more.

E

Edit interval

Edit interval opens the same editor in Data Acquisition V3 and Order Management. Use Start, End, and Quantities to correct recorded work. Production and Preparation describe its type. A dot beside a tab marks unsaved edits.

Learn more.

Email change waiting for confirmation

The new email has been requested but is not confirmed yet. Keep using your current email until you confirm the link sent to the new address. Resend requests another message after the displayed wait. Cancel change stops the pending request.

Learn more.

Energy monitor

Optional device measuring electrical energy, voltage, power factor, and frequency.

Learn more.

Energy wastage

Frontend label for energy consumed while not producing. Its exact state coverage is unconfirmed; the FAQ idle calculation is illustrative.

Learn more.

ERP / Enterprise Resource Planning

The company's business system from which order spreadsheets are exported for ERP Uploads.

Learn more.

Est. / Estimated

An estimate, as in Est. Hourly Revenue and Est. Hourly Cost; not a measured amount.

Learn more.

Event

One Automator trigger. States: New, Acknowledged, Resolved; a resolved event can be Reopened.

Learn more.

Event Inbox / SLA Breaches

List of Automator events and count of open events past their response due time.

Learn more.

F

Feedback

Bugs, improvements, and feature requests sent to Novo AI. Sent, In review, Resolved, Closed are conversation states.

Learn more.

Focus Mode

Hides surrounding interface to enlarge the analysis.

Learn more.

Forecaster

Shows expected start and finish times from current work, waiting jobs, and planned shifts. It updates by itself about every minute and never changes your plan or delivery dates by itself. Open How does the Forecaster work? for its explanation.

Expected and Planned Times

Expected times show when work is likely to happen, including delays. Planned times show the schedule you set. The delivery date is the customer promise; the planned end is the finish in your plan.

At Risk

at risk (previously tight) is an amber warning. The order is not late yet, but the remaining work barely fits or an earlier step is not planned. The help calls this At risk. Only the name changed; the warning means the same thing.

On Time, Late, and Finish Not Known

  • On time: green; expected to finish before the date.
  • Late +3 h: red; expected to finish three hours after the date. Late, date passed means the date has passed and the order is unfinished.
  • Finish not known: blue; the date is ahead, but no expected finish is available, for example because a step is still in a hall pool.

Missing the delivery date is red. Missing only the planned end is amber.

Times May Be Too Early

Times may be too early (previously Forecast not reliable) warns that an order may finish later than shown. Check for steps without a machine or date. Missing planned durations, missing shift plans, or delayed production entries can also make expected times too early.

Steps on a Machine

The step count tells you how many of the order's steps have a machine. It does not count finished steps. Work without a machine can make the expected finish too early.

Partly Planned and Not Planned at All

Partly planned means some steps still lack an assignment. Not planned at all identifies orders with a delivery date but no operation assigned to a machine or hall pool. They appear on no planning board.

Earlier Operation Not Planned

Earlier operation not planned warns that the displayed times assume the earlier step is already finished. Check earlier steps that have no machine yet or are still in a hall pool before relying on later finishes. Long-held and never-started machine steps still occupy time in the forecast.

Never Started and No Planned Start

Never started and No planned start appear only when Follow planned dates or Delivery date first is selected under View options → Planning in Assignment Gantt. Never started identifies work whose planned start is long past; the forecast assumes it starts as soon as its machine is free. No planned start means the forecast places it after the machine’s dated work. With Follow the queue or Follow the queue, not before the planned date, neither note appears and the operation keeps its place in the queue. Both types of work still get expected times.

On Hold for a Long Time

On hold for a long time (previously On hold too long) means paused work has passed Hold limit (working hours). It remains in the forecast and keeps its queue position, so later work still waits for it. The limit only controls when the note appears. Admins set it under View options → Planning in Assignment Gantt using machine working time, then choose Save.

Based On

Based on lists assumptions behind a step’s expected times, such as a long hold, a missing planned start, or missing earlier work. The same assumptions appear at the warning icon. Read them before relying on the forecast.

Why This Time

Why this time explains what a step waits for: its machine, an earlier step, or the next shift. Earlier operations of this order lists the preceding work and its progress. Hover over a Planner card’s date tab or clock to read these details.

Waits for an Earlier Operation

Waits for an earlier operation means an earlier step is not on a machine yet or remains in a hall pool. The later step still has a forecast, but its times may be too optimistic.

No Forecast

No forecast marks hall-pool work or a forecast that is not available right now. It does not mean that work is finished. Pool work gets a forecast once it is on a machine. Until an expected end exists, the Planner only compares the date with today.

Read the card explanation.

Load and Earliest Availability

Load in Assignment Gantt compares booked working time with visible shift time. The machine summary shows work still booked by the forecast. When work has no expected end, the machine’s displayed free time is only its earliest possible availability.

Save as Plan

Save as plan saves the displayed queue and Watchmen planned-date changes after review. The searched sequence can also change operation priorities as shown. Original operation dates and delivery dates stay unchanged. Undo restores the saved changes.

Jobs in Parallel

Jobs in parallel is how many assignments a machine can run at the same time. Administrators set a whole number from 1 to 100 in machine configuration; the forecast uses this capacity.

Learn more.

G

GDPR / DSGVO

General Data Protection Regulation, called Datenschutz-Grundverordnung in German; a label on sign-in pages.

Learn more.

Global rule

An Automator rule with no selected machines, applying to all active machines.

Learn more.

Good qty. / Gutmenge

Parts produced without defects, separate from material and work scrap.

Learn more.

H

Handed over

Handed over marks the finished part on the original machine when remaining work has been passed on. On an order, the neutral badge identifies handed-over steps. It does not mean that the whole step or order is finished.

Learn more.

Hall / Halle

Production area grouping machines for Hall Plan, planning columns, and Hall Pools.

Learn more.

Hall Plan / Hallenplan / Kiosk

Hall overview that can run unattended with an API key instead of a login; operators cannot access Hall Plan.

Learn more.

Hall Pool

Shared hall queue. An assignment has no specific machine until a machine in that hall claims it from PDA. In Assignment Planner, Hall pools lets you choose the halls and their placement. In the board puts pools beside their machines; Beside the list keeps them beside the unassigned list while machines scroll. Pools do not count toward the 25-machine limit. Collapse pool leaves a narrow strip that still accepts cards; Expand pool shows its cards again.

Learn more.

Hr / Std / Hours

Hours in duration displays. Std Run Time is a different label meaning Standard run time.

Learn more.

I

Improve plan

Improve plan opens the same comparison in Assignment Planner and Gantt. Today marks the current company rule; Best result marks an improvement in late orders and delay after saving. Review 2 · What changes before Save as plan.

Learn more.

Immediate order

An order created at the machine through Find/Create Immediate Order when no planned order is available.

Learn more.

IMPACT / Impacted

ERP check badge: a calculated planning value would be affected by a change.

Learn more.

incl. / inkl. / Including

Including, for example Assignment Planner access including Assignment Gantt.

Learn more.

Industrial minutes / Industrieminuten

One industrial minute is one hundredth of an hour, or 0.6 ordinary minutes. 500 equals 300 ordinary minutes.

Learn more.

Input Quantity / Cycle Count / PDA Entry / BDE-Eintrag

Operator-entered quantity versus sensor-detected cycles. Switching the progress source changes the display only.

Learn more.

Interval / Intervall

One recorded work session with start and end timestamps. Deleting it cannot be undone.

Learn more.

Interval Performance

Production time divided by total interval duration; differs from the overall PRO metric.

Learn more.

Info / Warning / Critical

PDA Assist severity levels: Info is silent, Warning shows an orange banner, and Critical shows a red banner with a flashing border. Warning and Critical can also play sound when enabled.

Learn more.

Initial order priority (new orders) / Initial operation priority (new operations)

Import values for new orders or operations with empty priority cells, or when no priority column is selected. An empty initial operation priority uses 100. They do not replace invalid entries or change existing priorities.

Learn more.

J

Job Context

Notes from order, work order, operation, and assignment, shown together at the machine.

Learn more.

K

Kanban / Tickets

Issue board with Open, In Progress, Resolved, Closed, and Archived tickets. Internal and External/Support types can link to machines or be moved into the Knowledge Base.

Learn more.

KB / WDB / Knowledge Base / Wissensdatenbank

The company's documents, images, and notes connected to machines, orders, and products. WDB is the German short tab label.

Learn more.

Kind / Machine

Kind distinguishes a Machine that can collect AVA readings from a Work center without an AVA.

Learn more.

Knowledge Base upload states

Queued, Reading, Splitting, Indexing, Linking, Review, Ready, Failed track processing; upload alone does not mean ready.

Learn more.

Visual relationships between documents and production items. Automatically suggested links must be confirmed or rejected.

Learn more.

KPI / Key Performance Indicator / Kennzahl

A production indicator such as OEE, availability, or cycle time.

Learn more.

kWh / Kilowatt-hour

Kilowatt-hour: energy consumed over time. W and kW are units of power.

Learn more.

L

Last Heartbeat

Most recent time the machine device reported; separate from the machine's production state.

Learn more.

Leaderboard

Admin-only machine and operator rankings. Current sidebar availability needs confirmation.

Learn more.

Legacy / V1

Older Orders V1 and single-machine ERP Upload versions, kept reachable but superseded.

Learn more.

License Key

The company's licence identifier, distinct from an API access key.

Learn more.

Live Data

Mode streaming current machine readings.

Learn more.

Live order

An order with an interval running right now.

Learn more.

Live Utilization

Share of machines producing at this moment; not an average across the reporting period.

Learn more.

Local IP / Lokale IP / MAC

Network details used to identify a registered hall display; distinct from its production figures.

Learn more.

Lookback Cycles / Gap Threshold

For slow-cycle checks, the number of recent cycles to inspect (1 to 1000) and a positive multiple of expected cycle time. A multiple of 2 means twice as long.

Learn more.

Lts. / Litres

Litres, used for coolant output in Sustainability Check inputs.

Learn more.

M

MA / Mat. / Material-Ausschuss

Material Scrap: parts rejected because of the material, separate from Work Scrap (AA).

Learn more.

Machine features

Custom sensor readings with name, unit, thresholds, precision, and multiplication factor, such as temperature.

Learn more.

Machine rating

Configured machine targets compared with actual dashboard values, not measurements.

Learn more.

Machine states

Machine states shows what the machine actually did during booked work, including idle or off time.

Learn more.

Machine tags / Order tags

Company labels for grouping and filtering machines or orders.

Learn more.

Max. / Maximum

The highest value in cycle statistics.

Learn more.

Mid Booking / Zwischenbuchung

Books quantities while work continues by closing and restarting the interval. If restart fails, bookings remain saved; press Start.

Learn more.

Min / Minutes

Minutes in duration displays. Do not confuse ordinary minutes with Industrial minutes.

Learn more.

min prep / Min. Vorb.

Minutes of preparation or setup for an operation.

Learn more.

Min. / Minimum

The lowest value in cycle statistics. Min. Zykluszeit means minimum cycle time; Min. in a duration can mean minutes.

Learn more.

min/pc / Min./Stk

Minutes per piece, used for planned operation timing.

Learn more.

Minimum shift length / Stop that ends a shift / Maximum shift length

Minimum shift length is how long the machine must work before the first stop ends the shift. Before then, only a stop reaching Stop that ends a shift ends it; shorter stops count as off time within the shift. Maximum shift length starts a new shift even if work continues, at most 24 hours. All values must exceed 0. The minimum and stop length cannot exceed the maximum.

Learn more.

Minimum true duration

Time an Automator condition must remain true before an event is created.

Learn more.

MTTR / Mean Time To Resolution

Automator average time from an event triggering to its resolution.

Learn more.

N

New operations in the queue

The import’s choice of where work enters machine queues and hall pools. Find it in Operation Fields, directly below the Operation Description row. By sorting is preselected and inserts work using the displayed rules without re-sorting existing operations. At the start places work behind running operations; At the end adds it at the back. Placement never changes priorities or dates. Company sorting: appears when the rules match the company sorting. Own sorting: identifies rules chosen for the import that differ from the company’s. Sorting: appears for the standard rules when no company sorting exists.

Learn more.

N/A / k. A. / Not available

A value is unavailable; it is not the same as zero.

Learn more.

Needs Attention / Handlungsbedarf

The former summary for several production and date warnings. On Orders & Products, Forecaster now counts open orders expected to miss delivery or already past their delivery date. Other warnings remain useful when reviewing individual assignments.

Learn more.

NEW / NEU / New

ERP check badge: a new record would be created.

Learn more.

New length

New length: shows the duration that your edited start and end would produce. It appears only when both times exist and you change a time. The saved values remain visible above the controls.

Learn more.

Newsletter report version

Newsletter report version is your personal choice of Version 1 or Version 2 for weekly and monthly report emails. Save it in your profile → Newsletter Preferences card with Save Preferences. Both subscriptions use the same version, and you can switch back at any time.

Learn more.

No. / Nr. / Row number

Row number in Admin Panel tables. Nr. on an operation can instead be its sequence number.

Learn more.

O

OEE / Overall Equipment Effectiveness / Gesamtanlageneffektivität

Headline score combining Availability, Performance, and Quality. The exact server formula remains unconfirmed; Watchmen's time definitions differ from textbook OEE.

Learn more.

Order / Auftrag / External Order ID

Overall job, identified by its order name; contains work orders, operations, and assignments.

Learn more.

Order Planned dates / Operation Planned dates

Order dates are shared across the order; operation dates belong to one step and can be used to sequence steps.

Learn more.

Order priority / Operation priority

Independent urgency values for the whole order and one production step. The planner shows P for the order and a dashed OP for the operation. Order forms also let you choose the operation priority. Its dashed OP indicator appears beside the operation name; new operations start at 100. When both priority filters are set, work must match both.

Learn more.

Orders today

Orders today shows running and finished work booked today on a machine or work center, across the whole day.

Learn more.

Org Stats / Organization Statistics / Organisationsstatistiken

Admin dashboard for company-wide production, energy, and impact indicators. Live Utilization is a snapshot; Downtime Reduced, Revenue Recovered, and Still reachable describe different recovery and potential figures.

Learn more.

Over Production / Quantity exceeded

Booked quantity exceeds plan. Choose Put on hold or Mark as finished after reviewing the quantities.

Learn more.

Operation at risk

Automator template that combines production 15% behind pace with cycles 25% slower than the baseline. Its conditions are separate from the Forecaster's delivery assessment.

Learn more.

P

Partly done / Done on

Partly done: shows good parts already made and where the rest is waiting. When all parts are finished, Done on lists the machines and their quantities.

Learn more.

P / Order priority

Priority chip for the overall order, independent of the operation's OP or AG priority.

Learn more.

PCS / pcs / Stk. / Pieces / Stück

Produced-piece counts. PCS on Hall Plan and kiosk figures stays unchanged across languages; pcs can appear as Stk. elsewhere.

Learn more.

PDA Assist

PDA Assist (previously PDA Assistant) combines interval assistance and warnings for a machine. Administrators configure them separately. Operators can choose suggested times and review, snooze, or mute warnings.

Learn more.

Right now

Right now in the PDA Assist dialog shows current assistance information. Open it at the right edge of the PDA page. An amber dot means automatic ending is counting down; green means no countdown. A brief glow follows a corrected time.

Learn more.

Setup (preparation)

Setup (preparation) groups the allowed setup times separately from production in PDA Assist. Administrators can change the two groups independently. These options also guide reviews of past intervals.

Learn more.

Other times

Other times lists earlier alternatives to the most recent main choices, newest first. They are real machine events within the asking limit, with up to 20 offered times in total. Times outside the automatic limit require your choice.

Learn more.

Adjusted / Auto-ended / Improved

Adjusted marks a start or end changed by interval assistance. Auto-ended marks a production interval ended after the configured off or idle period; quantities may still need booking. Improved marks a change applied when reviewing past intervals. Open the explanation for the time and reason.

Learn more.

Improve intervals

A check of recorded intervals against machine activity for up to 60 days. It proposes changes and shows their impact before you apply them. Anyone with machine access can review one machine; only administrators can review several and apply the best options everywhere.

Learn more.

Overlaps (warning)

More intervals ran at once than the machine's parallel capacity. Parallel work may be correct. These suggestions start unticked and are excluded from Apply best everywhere.

Learn more.

Peak Optimizer

Admin-only comparison of operators over a period to find top performers and bottlenecks.

Learn more.

Pinned items

Pages, machines, and hall plans pinned to the top of personal navigation.

Learn more.

Planned Start / End / Actual Start / End

Planned dates describe the schedule; actual dates describe recorded work. Grouped order dates span the order; assignment rows have their own windows.

Learn more.

Polling interval

How often an Automator rule is checked.

Learn more.

Prep / Prep. / Vorber. / Vorb. / Preparation / Vorbereitung

Setup before production. Vorber. is used on German PDA buttons; Vorb. (previously Rüst) appears on planning cards. Both describe preparation.

Learn more.

Planned quantity reached

Planned quantity reached asks after Stop when good parts plus all scrap across the operation’s intervals reach or exceed the plan. Complete closes it; Keep on hold leaves it open for later booking. Closing the question also keeps it on hold.

Learn more.

Prep / Start / Stop / Continue

Prep starts preparation and Start starts production. In the quantity dialog, Continue books quantities, ends the running interval and immediately starts a new one. Stop books and ends the interval, then asks about completion when the plan is reached. Cancel closes without booking.

Learn more.

Position in the queue

Position in the queue shows where a waiting step stands in Up next. Running steps have no number.

Learn more.

Priority

An urgency number interpreted using the company’s Which number is more urgent? setting. Higher number = more urgent is the default; Lower number = more urgent reverses it. Administrators choose the direction and levels in Admin Panel → Priority Levels.

Learn more.

PRO / Performance / Leistung

Share of switched-on time used for production or preparation. PRO does not mean Production or produced pieces.

Learn more.

Prod / Prod. / Production / Produktion

Production, distinct from the PRO abbreviation for Performance.

Learn more.

Production time in intervals

Production time in intervals is the production time recorded in a work center’s operation intervals. It is not a sensor measurement. Preparation hours are shown separately when present.

Learn more.

Production without an order

Production without an order is production time during which no interval of an operation was running on the machine. Version 2 counts stretches of at least 5 minutes, using the same rule as Improve intervals, capped at each day’s production time. It appears only if the company recorded at least 5 intervals of real operations in the report period, excluding test orders. Work centers are excluded; a missing section does not mean every production hour was covered by an interval. Test-order intervals still cover machine time even though the orders are excluded from report lists and counts.

A machine’s chart bar and Without order (h) value turn orange at both 20% of its production time and 2 hours. It is also listed under What needs attention and In focus.

Learn more.

Product / Produkt / External Product ID

What is manufactured; External Product ID is the product name.

Learn more.

Product information

Hall Plan setting for showing the active order's product image, product name, and operation sequence (#) next to the machine image. On requires a product image. With Off, or without an image, the sequence appears in the order card. Order and operation priority always stay in the order card.

Learn more.

Products more / less produced than detected

Difference between operator-entered production quantities and sensor-detected cycles.

Learn more.

P{code} / P0–P9 / P1–P9

Priority-code labels in ERP presets, for example P1. Read them in the company's configured priority scheme.

Learn more.

Pulse

Raw machine-sensor signal over time, displayed below the timeline with resolutions of 1 minute, 30 seconds, 5 seconds, or 1 second.

Learn more.

Place in this queue

Place in this queue explains the number at the bottom left of a Planner card. It counts active work in that machine or hall pool. Numbers appear in queue-position mode without priority, operation priority or tag filters, with the usual status selection and no search in that area. Data Acquisition cards do not show them.

Learn more.

Q

Quantity left / Done here / Left

In the handover dialog, Done here counts good parts on the original machine. Left summarizes the remainder. Quantity left starts with planned quantity minus good parts, never below zero. Scrap does not reduce it. Change it for needed replacements or leave it empty if unknown.

Learn more.

Qty / Quantity / Menge

The number of units. Distinguish planned, entered, counted, good, and scrap quantities.

Learn more.

Quality / Qualität

The dashboard tooltip states 95% and directs changes to an admin. Automatic replacement from quantities and the setting location are unconfirmed.

Learn more.

Queue Order and Operation Priority Stay in Step

Queue order and operation priority stay in step is an administrator setting, on by default. In the Planner’s queue-position mode, dragging a step can change its operation priority, and changing its card priority can reposition its parts in accessible queues. Turning it off separates the two actions. Undo in a drag’s priority notice restores priority and keeps the dropped position.

Learn more.

Queue Position / Queue load

Sort by Queue Position shows the saved card sequence. Queue load describes the planned work in that queue. In Assignment Planner, running and on-hold cards keep their queue positions and can be reordered within their column. Data Acquisition V3 has separate choices for where these orders appear.

Learn more.

Put in queue

Put in queue chooses where a reopened operation returns: By company sorting, At the top, or At the bottom. Company sorting uses its saved rules without changing priorities, dates, or the company sorting itself.

Learn more.

R

Re-sort

Re-sort (previously Sort by priority and date) proposes a queue sequence from Sort rules or one priority or date. Under Rules from, My sorting uses your Planner rules; Company standard copies the administrator’s rules when available. Changed marks temporary rules matching neither choice. These edits apply to this re-sort only and do not replace saved sorting. Clear Can move to keep an operation in place. Re-sorting does not change priorities or keep sorting automatically.

Learn more.

Ratio thresholds

Read the selected condition: setup and cycle checks compare time with a plan or baseline; production checks measure a shortfall against pace. Order progress compares completion with the elapsed schedule. The same percentage does not mean the same thing for every measure.

Learn more.

Report version / Version 1 / Version 2

Version 1 is the familiar Excel report. Version 2 starts with findings that need attention and includes targets, shift comparisons, cycles, reasons and orders. Recent weekly and monthly reports also show planned work for the next 7 days; exports do not.

Report version in the export dialog on the Timeline Analysis page applies to that export only. Version 2 beside a period in the archive marks a report in the new version. Rows without it are Version 1. What you get and Download an example help you compare the versions before choosing.

Learn more.

Revision

Revision identifies an updated report in the archive. Its number increases when the report is rebuilt with changed contents. Every scheduled report is checked automatically once, 3 days after it was sent. If the data changed, the report gets a new revision. If nothing changed, it stays as it is. As an Administrator, you can also select Rebuild with current data at any time. For example, Revision 3, updated … shows its revision and update time. The first revision has no revision line. Downloads always contain the latest revision; emails already sent are not sent again. Version 2 beside the period refers to the report layout.

Learn more.

Report archive

Only Administrators can open Report archive. Other users do not see it.

Report archive contains Weekly, Monthly, and Export reports. Scheduled means a scheduled report; By user means someone requested it.

StatusMeaning
QueuedWaiting for creation to start.
BuildingBeing created.
ReadyReady to download.
FailedCreation did not finish successfully.
RefreshingBeing checked against current data.

Rebuild with current data checks an existing report and updates it if the contents changed. Not emailed describes email delivery, not creation status. A failed refresh keeps the previous revision available.

Learn more.

Requires active shift

Automator checks pause while the machine is outside its active shift.

Learn more.

Revenue Recovered / Still reachable

Already recovered value versus remaining modeled potential; the latter includes half the remaining idle time.

Learn more.

Rework Qty

Quantity needing rework; do not assume it is added to the card total without a confirmed rule.

Learn more.

Roadmap

Public Novo AI plan: Ideas, Planned, In progress, Released. Users can upvote items.

Learn more.

running

The active shift is still in progress. Its end follows the machine's active shift settings.

Learn more.

Running and on-hold orders

Running and on-hold orders: Orders in progress or on hold. Example: an order that was started and is on hold for a tool change. In Data Acquisition V3 queue sorting, choose Keep in place or At the top. As a sort rule, this group offers At the top or At the bottom and comes before the waiting-order rule.

Learn more.

Recently completed

Recently completed shows the selected machine’s last five completed operations, newest first. Its cards are read-only, with Set on hold available when reopening is allowed and the part was not handed over.

Learn more.

Reopen completed operations

Reopen completed operations is the template switch for Set on hold in Recently completed. It starts on and works separately from Change the order status.

Learn more.

Reopened

Reopened marks an operation reopened after completion or cancellation. Its explanation shows who reopened it, when, the machine when available, and its queue placement. The badge appears on PDA and Planner cards until the operation is completed or cancelled again.

Learn more.

S

Scrap / Ausschuss

Rejected parts split into material scrap MA and work scrap AA.

Learn more.

Search in

Assignment Planner’s search-area choice: Unassigned searches the unassigned operations list, Hall pools searches pooled work, Machines searches work on machines, and Everything searches all three. Search matches order, product, or customer, not machine names. Your choice is remembered; the default is Unassigned.

Learn more.

Sec / Sek / Seconds

Seconds, the display unit for cycle times.

Learn more.

Sensor powered by machine

Use when the sensor loses power with the machine; a missing signal then appears as Off instead of Unknown.

Learn more.

Seq / Nr. / Sequence / Arbeitsgangfolge

An operation's step number within a work order, for example 10, 20, 30. In Hall Plan, the operation sequence is shown with # beside the product or in the order card, depending on Product information and whether the product has an image. The German name is Arbeitsgangfolge.

Learn more.

Shift / Whole day

A shift is a named work period with start, end, and optional breaks. Whole day covers the entire day.

Learn more.

Shift group / Schichtgruppe

Weekly pattern assigning shifts to weekdays, attached to machines.

Learn more.

Shift Planner / Scheduler / Schichtplaner

Page for assigning shifts and operators to machines by day or week.

Learn more.

Show more cards

Show 40 more, or a smaller remaining number, reveals the next cards in a Planner queue. Each queue initially shows 40 matching cards. Its count and summary include every card in the queue, also the ones not shown yet.

Learn more.

Silence / Unsilence

Temporarily mute or restore one alert type or all alerts for a machine.

Learn more.

SLA / Service Level Agreement

In Automator, the number of minutes responders have before an open event is overdue.

Learn more.

Snooze

Temporarily hide a warning from the banner and silence it for the configured duration. It stays listed under Snoozed and returns if the problem remains. Resume now restores it sooner.

Learn more.

Start Preparation / End Preparation / Start Shift / End Shift

Explicit actions for preparation and shift boundaries; Prep starts a preparation interval, while Start starts production.

Learn more.

Status / Unplanned / Planned / Released / In Progress / Hold / Completed / Cancelled

Order and assignment states: Ungeplant, Geplant, Freigegeben, In Bearbeitung, In Wartestellung, Abgeschlossen, Storniert. Order status follows assignments; Released timing is unconfirmed.

Learn more.

Std Run Time / Standard run time

Planned production time per unit.

Learn more.

Still running

Still running (previously Ongoing) is the same wording on every screen showing a running interval or order: Data Acquisition, Order Management, and Orders & Products. For an interval, it means no end has been recorded. Its end is set when you stop it. The interval editor cannot end it.

Learn more.

Sum / Summ. / Totals

Totals row in order analysis; Avg. or Ø is the averages row.

Learn more.

Sustainability Check

Optional company inputs for the CO₂ estimate, including waste, renewable share, coolant, transport, and material efficiency.

Learn more.

Stays on top

The former Stays on top label has been removed from the Planner’s priority-and-date preview. Running and on-hold work is sorted with all other active work. In queue-position mode, cards follow the dragged order.

Learn more.

T

Tap to change

Tap to change replaces Double-tap to edit in Data Acquisition V3. Tap a start or end time once to open that part of the interval editor.

Learn more.

Templates / Auto-resolve / Notify on resolve / Escalation

Automator presets and responses: close on a cleared condition, notify on closure, or notify another group when overdue.

Learn more.

Timeline / Production / Idle / Off / Stopped / Preparation / Unknown

State bar: Production green (Produktion), Idle orange (Leerlauf), Off/Stopped red (Aus/Gestoppt), Preparation blue (In Vorbereitung), Unknown grey (Unbekannt).

Learn more.

Timeline Analysis / Trend Analysis

Reports examining machine states within a period versus KPI trends across days.

Learn more.

Timeline ranges / Time range / Idletime Distribution

Duration buckets, such as 1–5 or 5–30 minutes, used to count downtime frequency and duration.

Learn more.

Timeline reason / Downtime reason / Stillstandsgrund

A label explaining a downtime period. Administrators maintain shared reasons and choose where operators may select them. Removing a reason from a machine's selection does not remove past labels. Deleting the reason keeps past entries but removes their reason.

In Hall Plan, Downtime reason is a card in V2 and V3 showing the reason the machine operator chose on the PDA page for the current downtime. It appears only while the machine is idle or off, if a reason was chosen and the card is enabled. The previous shift never shows it.

Learn more.

Code / Category

A reason's optional Code, such as F12, is unique within the company and uses uppercase letters. Category groups reasons for selection, for example Mechanical or Material. Chart explanations show both when available.

Learn more.

All reasons (default) / Only selected reasons

All reasons (default) includes every company reason and future additions. Only selected reasons limits operators to a fixed list with at least one reason. Deleting the last selected reason leaves that restricted list empty until an administrator changes it.

Learn more.

Available on machines

The machines where operators can select a reason. Unticking a machine marked All reasons gives it a fixed list of the other current reasons; later additions no longer appear automatically.

Learn more.

Break settings / Label breaks automatically

Break settings lets administrators enable Label breaks automatically for the company. Finished idle or off downtime during a scheduled shift break can receive that break's Downtime reason. No downtime reason skips that break. A person's choice always takes priority.

Label only the break (recommended) gives the break's reason only to the overlapping break time and its tolerance. Label the whole downtime gives it to all of an overlapping downtime, which can hide a longer breakdown.

Tolerance

In Break settings, Tolerance adds 0–15 minutes before and after a break when only the break is labelled. It starts at 5 minutes. The downtime must overlap the actual break; touching only the tolerance is not enough.

Learn more.

Timeline rules

Automatic reasons selected by specific reason rule, then its DEFAULT rule, then Global rules, for Off, Idle, or Preparation.

A reason chosen by the machine operator or set by hand takes priority. When automatic break labels are enabled, an eligible break's reason comes next. Downtime reason rules apply to the remaining idle or off time; without a matching reason, the time stays unlabelled.

Learn more.

Total / Planned / Input / Counted

Assignment quantities: planned target, entered quantity, detected count, and total input plus MA plus AA.

Learn more.

Trust this device for next 30 days

Skip the second authentication step on the trusted device for 30 days.

Learn more.

U

Unassigned operation

An operation without a machine, listed in the Assignment Planner's left panel.

Learn more.

Unbound / unlabeled machine time

Machine time between recorded intervals belonging to no order.

Learn more.

Unlabeled timeline warning

Marker for downtime without an assigned reason.

Learn more.

Up next

Up next shows the machine’s queue in execution order so you can see what comes next, regardless of the selected day.

In Version 2 weekly and monthly reports, Up next is the outlook for the 7 days after the report period. It preserves the plan from when the report was first created, even after a rebuild. Exports and older periods omit it. See Report Versions.

Learn more.

util. / Util. / Ausl. / Utilization / Auslastung

Planned load of a machine queue, based on planned durations, not recorded production.

Learn more.

V

View options

In Assignment Gantt, View options → Board contains your own bar and row-height choices. They apply at once. Only Admins can change company settings under View options → Planning and choose Save. Everyone else who can open Gantt sees the values read-only with Ask an admin to change these. A preview is identified by The board is showing a preview: <rule>. with the rule’s name.

Learn more.

W

Work left / Expected end

Work left is planned work minus work already recorded. A dash means it is unknown. In planning proposals, Expected end compares the forecast with today’s sequence against the forecast after applying. Planned ends and delivery dates are separate and appear in Details.

Learn more.

Waiting on a previous operation / Blocked by

⚠️ Waiting on a previous operation means a step with a lower number in the same work order is neither completed nor cancelled. An earlier step without an assignment also counts as unfinished. Start anyway remains available; review the dependency before using it.

In Data Acquisition V3, the Waiting on a previous operation sorting rule offers At the bottom or At the top. It comes before priority and date. If you also add Running and on-hold orders, that rule comes first. With Sort by Queue Position on, Orders waiting on a previous operation offers Keep in place or At the bottom, preserving queue order within each group. Both options are off until you choose them and are saved for your account.

Learn more.

Webhook

Alert delivery to another system by URL, optionally with Basic, Bearer, or custom-header authentication and a payload template.

Learn more.

Wi-Fi / WLAN

Wireless network information for a registered hall display.

Learn more.

WO / Work Order / Arbeitsauftrag

The part of an order for one product, with a planned quantity and operations.

Learn more.

Work center

A Work center is a workplace without an AVA. It shows today’s worked orders and the waiting queue and can receive assignments. It has no sensor KPIs and is excluded from state counters and sensor analytics. Sensor-based rules never trigger for it. Version 2 reports show only work-center operations, from their intervals, under Summary → Work centers and on their own pages. They have no OEE, availability, performance, machine states or cycles anywhere in the report, and are excluded from production without an order.

Learn more.

Worked

Worked shows steps with recorded work on the selected day, even if they started earlier.

Learn more.